Gas power built for data centers, under construction
dc-gas-construction
Unit: GW · Quarterly · Since Q3 2026
Generating capacity of gas-fired power plants for US data centers that is under construction, in GW.
- Covers
- US gas-fired plants tied to data centers, decided project by project (unit by unit where only some of a plant's units are for data centers): classified in the plant records as serving data centers, or tied to them by a company statement or a regulator's approval.
- Method
- The capacity of each counted project's units under construction, added up, in GW to one decimal. A project's units are counted under their own status, so one project can add to more than one of these numbers. Projects whose names suggest data center use are checked by hand before they count, so a new one can be added late. A new value is worked out each time the plant records are updated.