Nuclear restarts and uprates contracted by data center companies

nuclear-restart-uprate

Unit: GW · Daily · Since 15 Oct 2026

Nuclear capacity that data center companies have contracted from closed reactors being brought back and from added output at running reactors, in GW.

Covers
US deals with a named data center buyer, a named plant or developer and a stated size. Non-binding frameworks, a buyer's own targets and plants with no data center buyer signed are left out.
Method
The megawatts of every restart and uprate deal, added up, in GW to two decimals, from a list of deals WattSaid keeps by hand from public announcements. A deal counts from its announcement, whatever year power is due to start, so this is contracted capacity, not power delivered. Where one agreement covers both running output and an uprate, only the uprate is counted here. The number changes only when a deal is added or revised.